BMP ID |
Short Title |
Text of BMP |
---|
10355 |
BMPs constructed around perimeter |
"BMP's will be constructed around the perimeter of the site prior to or at the beginning of construction." |
10356 |
BMPs used will vary |
"BMP's used will vary according to the location." |
10357 |
BMPs will remain in place |
"BMP's used . . . will remain in place until the pad reaches final reclamation." |
10372 |
Cleanup |
"Cleanup will consist of patrolling the roadways, access areas. and other work areas to pick up trash, scrap debris, other discarded materials, and ... |
10365 |
Collection and disposal of wastes |
"Wastes will be . . . regularly collected and disposed of at offsite, suitable facilities." |
10378 |
Communicate any change in access to the Town |
"4. . . . GW will act in good faith and communicate any change in access to the Town, to the extent such revised access includes Town Roads." |
10359 |
Designated storage area for dry bulk chemicals and miscellaneous fluids |
"In accordance with COGCC Rule 1002.f. (2)A.& B.,shall provide a designated storage area for dry bulk chemicals and miscellaneous fluids." |
10373 |
Disposal of materials |
"These [trash, scrap debris, other discarded materials, and any contaminated soil] materials will be disposed of properly and promptly." |
10371 |
Major overhauls offsite |
"Equipment will be transported offsite for major overhauls" |
10370 |
No major equipment overhauls |
"There will be no major equipment overhauls conducted onsite." |
10374 |
Pay for required road repairs |
"1. GW will pay for all required repairs to ensure any damaged roads are promptly brought back to their condition prior to operations." |
10366 |
Prompt cleanup of spills |
"If spills occur prompt cleanup ls required to minimize any commingling or waste materials with storm water runoff." |
10375 |
Protect wastewater manholes |
"3. GW will take appropriate steps to adequately protect wastewater manholes located along any of its access roads." |
10380 |
Provide a description of anticipated traffic |
"6. GW will provide the Town with a description of the anticipated traffic to be generated by the construction, completion, and operation of the ... |
10379 |
Provide an emergency response plan |
"5. GW will provide the Town of Hudson an emergency response plan prior to commencing operations." |
10367 |
Routine maintenance will be limited |
"Routine maintenance will be limited to fueling and lubrication of equipment." |
10358 |
Spill Prevention Control and Counter Measures |
"Spill Prevention Control and Counter Measures (SPCC) plans will be In place to address any possible spills associated with Oil and Gas operations ... |
10360 |
Storage area shall be covered |
"The storage area [for dry bulk chemicals and miscellaneous fluids] shall be covered to prevent contact of precipitation with chemicals." |
10361 |
Storage area shall be elevated |
"The storage area [for dry bulk chemicals and miscellaneous fluids] . . . shall be elevated above storm or standing water." |
10362 |
Storage area shall provide sufficient containment |
"The storage area [for dry bulk chemicals and miscellaneous fluids] . . . shall provide sufficient containment to prevent release of spilled fluids ... |