BMP ID Short Title Text of BMP
8100 300 foot buffer between the edge of the ROW and plants "Graham's Beardtongue: surface pipelines will be laid such that a 300 foot buffer exists between the edge of the ROWand the plants."
5287 A botanical expert must be on site when vegetation is cleared Project Implementation Phase: "3. Ensure that a botanical expert is on site when clearing of vegetation occurs in the vicinity of plant species of ...
5733 A Class III cultural resources survey must be conducted over all proposed surface disturbance areas. CULTURAL RESOURCES: "A Class III cultural resources survey, conducted by a qualified archaeologist, would be conducted over all areas proposed for ...
2463 A current aerial photo is necessary to show the proposed oil and gas locations. "c. Information Requirements.... The following information may be included as part of a Comprehensive Drilling Plan, depending on the circumstance: ...
2301 A minimum of 3 feet of backfill cover over a drilling pit "d. Drilling pit closure. As part of interim reclamation, drilling pits shall be closed in the following manner: (3)Minimum cover. On crop lands, a ...
1827 A pre-disturbance species composition required per site. Reclamation: "A pre-disturbance species composition list must be developed for each site if the project encompasses an area where there are several ...
4520 A variety of techniques may be applied to reduce impacts on oil and gas sites. Mitigating development impacts: "A variety of techniques may be applied to reduce or mitigate impacts of oil and gas activities in active production ...
4141 Abandoned road reclamation would require reshaping, recontouring, and resurfacing "Developed or Designed Roads: Reclamation of abandoned roads would include requirements for reshaping, recontouring, resurfacing with topsoil, ...
1820 Abandoned sites must be satisfactorily rehabilitated Reclamation: "Abandoned sites must be satisfactorily rehabilitated in accordance with a plan approved by the BLM. "
2641 Accomplish reclamation as soon as possible after disturbance; continue efforts until site is stabilized "Reclamation: All reclamation is expected to be accomplished as soon as possible after the disturbance occurs, with efforts continuing until a ...
2570 Address practices that reclaim and stabilize disturbed areas in reclamation plans Coalbed Methane: Reclamation: "Phased reclamation plans will be submitted to BLM for approval prior to individualPOD facility abandonment via a ...
2569 Address revegetation methods and soil treatments in reclamation plans Coalbed Methane: Reclamation: "Phased reclamation plans will be submitted to BLM for approval prior to individual POD facility abandonment via a ...
2736 Adhere to allowed control measures "Reclamation: Control measures would adhere to those allowed in the RFO Noxious Weed Control and Commercial Site Vegetation Control Environmental ...
1708 Adhere to regional noxious weed control measures Pipelines: "Prior to any treatment, the Operator, grantee, or lessee will be responsible for submission of Pesticide Use Proposals and subsequent ...
241 Adjust livestock grazing in heavily used areas. Livestock Management: "Adjust livestock grazing in heavily used areas to allow native vegetation a period of recovery."
5069 Adjust seeing timing depending on conditions. "Final Reclamation: Seed Application: Late fall is typically a good time of year to seed, however timing of seeding should be adjusted depending upon ...
5308 Advise permitted users to remain on existing roads 3.2.2 Uinta Basin Hookless Cactus: "3. Advise other permitted users of the area to remain on existing roads."
5068 After grading, seed or apply erosion control to soil. "Final Reclamation: Seed Application: Upon completion of final grading, soil surfaces should either be seeded, or erosion control measures should be ...
8515 Agencies must conduct thorough biological inventories of each proposed CBM field before production begins Wildlife: Doing it Right: "Fish, Wildlife, and Plant Inventories: In order to ensure the long-term viability of Montana's invaluable wildlife, state ...
8532 Agencies must establish clear and enforceable reclamation standards Legacy: Doing it Right: "Full Reclamation: To ensure complete reclamation of land disturbed by methane production, state and federal agencies must ...