582 |
Implement an adaptive management process for the JIDPA. |
The Bureau of Land Management (BLM) will implement an adaptive management process for the Jonah Infill Drilling Project Area (JIDPA) that will follow ... |
3787 |
Operators will use remote telemetry technology at all wells |
"Operators will utilize remote telemetry or equivalent technology at all wells to minimize well monitoring trips..." |
3786 |
Project-required traffic is limited to approved roads. Two tracks are prohibited without a ROW. |
"Project-required traffic in the JIDPA is limited to BLM-approved roads. Operators will continue to cooperate with the BLM to identify and prohibit ... |