2834 Avoid construction in highly scenic areas. "Natural Gas Operations: 1. Location: b. Where practical, avoid construction in highly scenic areas."
994 Avoid locating facilities near "prominent" features "Natural Gas Operations: 1. Location: e. Avoid locating facilities near "prominent" features."
2840 Avoid locating roads and pipelines on steep slopes. "Natural Gas Operations: 1. Location: j. Avoid locating roads and pipelines on steep slopes. Follow the contours of the land to reduce ...
2841 Avoid locating well pads on steep slopes. "Natural Gas Operations: 1. Location: k. Avoid locating well pads on steep slopes. Well pads on steep slopes can create large cut and fill slopes ...
960 Begin final reclamation when well production ends. "Natural Gas Operations: 3. Reclamation: g. When well production ends, begin final reclamation. Ensure the site is recontoured, stable, and fully ...
2845 Bury power lines in or adjacent to the road "Natural Gas Operations: 2. Operations: c. Bury power lines in or adjacent to the road to eliminate cross-country vegetation clearing and resulting ...
2839 Choose the best location for the road and its anticipated uses. "Natural Gas Operations: 1. Location: i. Do not reuse existing roads just because they are preexisting and you are hesitant to disturb new areas. ...
992 Consider facility ridgetop visibility. "Natural Gas Operations: 1. Location: c. Ridgetop facilities are highly visible from great distances because they are skylined. Roads, on the other ...
2854 Consider lower class roads, smaller pads, and interim reclamation. "Natural Gas Operations: 2. Operations: g. Minimize the footprint of energy development. To reduce wildlife habitat fragmentation, loss, and ...
2851 Consider operator-enforced speed limits during critical seasons. "Natural Gas Operations: 2. Operations: e. Reduce vehicle traffic in important wildlife areas and during critical wildlife use periods. Consider: 2) ...
2852 Consider using shuttle vans and buses to transport drilling rig workers and field service personnel. "Natural Gas Operations: 2. Operations: e. Reduce vehicle traffic in important wildlife areas and during critical wildlife use periods. Consider: 3) ...
2842 Construct the minimum road necessary. "Natural Gas Operations: 1. Location: l. Construct the minimum road necessary. Consider using two-track roads for exploration wells that could become ...
2853 Cover all production-related pits and tanks to exclude wildlife. "Natural Gas Operations: 2. Operations: f. Cover all production-related pits and tanks to exclude wildlife, regardless of pit or tank size. Migratory ...
958 Cover borrow ditches with topsoil and consider reseeding low use road surfaces. "Natural Gas Operations: 3. Reclamation: f. Borrow ditches should be covered with topsoil and seeded. Consider seeding the road surface for low use ...
2843 Drill multiple wells from a single well pad. "Natural Gas Operations: 2. Operations: a. Consider drilling multiple wells from a single well pad to reduce the footprint of oil and gas activity on ...
954 Fully recontour unneeded areas, respread topsoil over the entire pad and revegetate "Natural Gas Operations: 3. Reclamation: d. Interim reclamation should begin shortly after construction or establishing oil or gas production on the ...
952 Limit activities to only the area that is necessary. "Natural Gas Operations: 3. Reclamation: c. Limit activities to only the area that is necessary."
2837 Locate and construct roads to follow the contour of the landform or mimic lines in the vegetation. "Natural Gas Operations: 1. Location: g. Locate and construct roads and other linear facilities to follow the contour of the landform or mimic lines ...
2833 Minimize visual impacts. "Natural Gas Operations: 1. Location: a. Work with the operator to choose the best site access and facility location to mitigate for visual impacts."
100 No surface disturbance within 1,000 ft of the channel of streams, riparian or wetland areas "Condition of Approval: Surface-disturbing activities are prohibited within 1,000 feet of the channel of ephemeral, intermittent, and perennial ...