BMP ID Short Title Text of BMP
11124 Action plan if methane concentration increases "5.2 Water Well Monitoring. … If the methane concentration level increases by more than 5 mg/L between sampling periods, or increase to more than ...
11123 Action plan if testing reveals thermogenic or intermediate mix "5.2 Water Well Monitoring. … If the carbon isotope test results in a thermogenic or intermediate mix signature . . .an action plan shall be ...
11129 Additional post completion water tests "5.2 Water Well Monitoring. … Additional 'post completion' test(s) may be required if changes in water quality are identified during follow-up ...
11122 Annual testing if testing reveals thermogenic or intermediate mix "5.2 Water Well Monitoring. . . . If the carbon isotope test results in a thermogenic or intermediate mix signature, annual testing shall be ...
11139 Applicable federal regulations "4. Compliance with all applicable regulations of the BLM, BIA and the Southern Ute Indian Tribe when conducting operations on lands subject such ...
11077 Calculating degree of noncomformity with setback requirements "2.4 Legal Non-Conforming Uses and Setbacks: … The increase, if any, in degree of nonconformity shall be the net difference between the two . . . ...
11795 Compliance term "2. Compliance with the terms and provisions of all of the Commission's health, safety, welfare and environmental rules and regulations now or ...
11794 Compliance terms "1. Compliance with all terms, conditions and provisions of prior Commission Orders in Cause No. 112, including without limitation, the specific ...
11101 Comply with weight restrictions "3.6 Produced Water Hauling. In those instances where the utilization of a water hauling truck is required, McElvain agrees to strictly comply with ...
11120 Compositional analysis and carbon isotopic analyses "5.2 Water Well Monitoring. … If free gas or a methane concentration level greater than 2 mg/L is detected in a water quality testing well, ...
11131 Copies of water test results provided "5.2 Water Well Monitoring. … Within three (3) months of collecting the samples used for the test, copies of all test results described above ...
11081 County exercises good faith in performing road work from impact fees "3.1 Road Maintenance and Improvement Fees. County and McElvain have determined that specific land use activities by McElvain within the Infill ...
11094 County proves notice to McElvain "3.3 Submission of Information: . . . The County agrees to provide notice to McElvain of its intended projects and forecasted activity plan on an ...
11082 County shall control road impact work "3.1 Road Maintenance and Improvement Fees: . . . The County shall control the sequencing and timing of such [road impact] work"
11079 Demonstrate reasonableness of Well Pad expansion "2.5 Expansion of Existing Well Pads: … The reasonableness of the expansion [of existing Well ads] under the circumstances shall be demonstrated by ...
11073 Demonstrating requested need for new facilities "2.3 Use of Existing Infrastructure: . . .At the request of the County, McElvain shall furnish information demonstrating McElvain's requested need ...
11066 Density of well pads "2.1 Density. McElvain agrees that, except as provided in Article 2.2 herein or as may be otherwise permitted in the COGCC order approving McElvain's ...
11070 Density rule limitation shall not apply when County denies a permit application "2.2 Well Location; Exceptions: … The limitation contained in Section 2.1 shall not apply in any instance in which the County denies a permit ...
11103 Electric motors for artificial lift installations more than 1320 of distribution "4.1 Electrification. … McElvain agrees that if distribution voltage is not currently within 1320 feet of the proposed Well Pad, it will contact ...
11102 Electric motors for artificial lift installations within 1320 feet of distribution "4.1 Electrification. McElvain agrees that with respect to Infill Wells drilled after the Effective Date of this Agreement within the Infill ...
Page:<< Previous|1234|Next >>   Goto to page: