You are viewing BMP records related to the Memorandum of Understanding Between the Board of County Commissioners of La Plata County, Colorado and Energen Resources Corporation, 2007 publication.

BMP ID Short Title Text of BMP
10877 Action plan if methane concentration increases "5.2 Water Well Monitoring. … If the methane concentration level increases by more than 5 mg/L between sampling periods, or increase to more than ...
10876 Action plan if testing reveals thermogenic or intermediate mix "5.2 Water Well Monitoring. … If the carbon isotope test results in a thermogenic or intermediate mix signature . . .an action plan shall be ...
10842 Adoption of Road Impact Fee Program "3.3 Adoption of Road Impact Fee Program. The County is presently undertaking a feasibility study for the imposition of a county-wide impact fee ...
10875 Annual testing if testing reveals thermogenic or intermediate mix "5.2 Water Well Monitoring. . . . If the carbon isotope test results in a thermogenic or intermediate mix signature, annual testing shall be ...
10890 Applicable federal regulations "4. Compliance with all applicable regulations of the BLM, BIA and the Southern Ute Indian Tribe when conducting operations on lands subject such ...
10829 Calculating degree of noncomformity with setback requirements "2.4 Legal Non-Conforming Uses and Setbacks: … The increase, if any, in degree of nonconformity shall be the net difference between the two . . . ...
10889 COGCC-ordered remediation if monitoring reveals a possible lack of zonal isolation "[6] . . .If the monitoring reveals a possible lack of zonal isolation, the COGCC may then conduct or order any necessary remediation or other ...
11804 Compliance terms "1. Compliance with all terms, conditions and provisions of prior Commission Orders in Cause No. 1 12, including without limitation, the specific ...
11805 Compliance terms "2. Compliance with the terms and provisions of all of the Commission's health, safety, welfare.and environmental rules and regulations now or ...
10854 Comply with weight restrictions "3.7 Produced Water Hauling. … In those instances where the utilization of a water hauling truck is required, ENERGEN agrees to strictly comply ...
10873 Compositional analysis and carbon isotopic analyses "5.2 Water Well Monitoring. … If free gas or a methane concentration level greater than 2 mg/L is detected in a water quality testing well, ...
10884 Copies of water test results provided "5.2 Water Well Monitoring. … Within three (3) months of collecting the samples used for the test, copies of all test results described above ...
10833 County exercises good faith in performing road work from impact fees "3.1 Road Impact Fees. County and ENERGEN have determined that specific land use activities by ENERGEN within the Infill Application Area may create ...
10846 County provides notice of intended projects "3.4 Submission of Information: . . . The County agrees to reciprocate [ENERGEN provision of notice on travel routes and plans] and provide notice ...
10834 County shall control road impact work "3.1 Road Impact Fees: . . . The County shall control the sequencing and timing of such [road impact] work"
10831 Demonstrate reasonableness of Well Pad expansion "2.5 Expansion of Existing Well Pads: … The reasonableness of the expansion [of existing Well ads] under the circumstances shall be demonstrated by ...
10818 Density of well pads "2.1 Density. ENERGEN agrees that, except as provided in Article 2.2 herein or as may be otherwise permitted in the COGCC order approving ...
10823 Density rule limitation shall not apply when County denies a permit application "2.2 Well Location; Exceptions: … The limitation contained in Section 2.1 shall not apply in any instance in which the County denies a permit ...
10856 Electric motors for artificial lift installations more than 1320 of distribution "4.1 Electrification. … ENERGEN agrees that if distribution voltage is not currently within 1320 feet of the proposed Well Pad, it will contact and ...
10855 Electric motors for artificial lift installations within 1320 feet of distribution "4.1 Electrification. ENERGEN agrees that with respect to Infill Wells within the Infill Application Area requiring long-term artificial lift, it ...