2301 |
A minimum of 3 feet of backfill cover over a drilling pit |
"d. Drilling pit closure. As part of interim reclamation, drilling pits shall be closed in the following manner: (3)Minimum cover. On crop lands, a ... |
2267 |
Access roads should be practical and avoid erosion. All vehicles will not travel outside of the original access road boundary |
"e. Surface disturbance minimization. (4) Access roads. Existing roads shall be used to the greatest extent practicable to avoid erosion and minimize ... |
2279 |
Address the transportation of chemicals and materials, including loading and unloading |
"f. Stormwater management. (3)A....Pollutant sources that must be addressed by BMPs, if present, include: i. Transport of chemicals and materials, ... |
2373 |
After the drilling pit is sufficiently dry, the pit shall be backfilled. |
"d. Drilling pit closure....(2) Drilling pit closure on non-crop land. All drilling fluids shall be disposed of in accordance with the 900 Series ... |
2299 |
All areas compacted by drilling operations shall be cross-ripped. |
"c.Compaction alleviation. All areas compacted by drilling and subsequent oil and gas operations which are no longer needed following completion of ... |
2306 |
All disturbed areas must be kept free of undesirable plant species |
"f. Weed control. During drilling, production, and reclamation operations, all disturbed areas shall be kept as free of all undesirable plant ... |
2268 |
All oil and gas locations are subject to the BMP Practices requirements of Rule 1002.f.(2) |
"f. Stormwater management. (1) All oil and gas locations are subject to the Best Management Practices requirements of Rule 1002.f.(2). In addition, ... |
2303 |
All segregated soil horizons must be replaced to original positions |
"e. Restoration and revegetation....(1)Revegetation of crop lands. All segregated soil horizons removed from crop lands shall be replaced to their ... |
2290 |
BMP includes pollutant sources, regarding erosion and vehicle tracking |
"f. Stormwater management. (3)A....Pollutant sources that must be addressed by BMPs, if present, include: vii. Erosion and vehicle tracking from well ... |
2294 |
BMP includes pollutant sources, regarding ground disturbing maintenance activities |
"f. Stormwater management. (3)A....Pollutant sources that must be addressed by BMPs, if present, include: x. Ground-disturbing maintenance ... |
2293 |
BMP includes pollutant sources, regarding leaks and spills |
"f. Stormwater Management. (3)A....Pollutant sources that must be addressed by BMPs, if present, include: ix.Leaks and spills." |
2286 |
BMP includes pollutant sources, regarding outdoor processing activities and machinery |
"f. Stormwater management.(3)A....Pollutant sources that must be addressed by BMPs, if present, include: v. Outdoor processing activities and ... |
2282 |
BMP includes pollutant sources, regarding outdoor storage activities |
"f. Stormwater management. (3)A.... Pollutant sources that must be addressed by BMPs, if present, include: iii. Outdoor storage activities, including ... |
2288 |
BMP includes pollutant sources, regarding significant dust |
"f. Stormwater management.(3)A.... Pollutant sources that must be addressed by BMPs, if present, include: vi. Significant dust or particulate ... |
2291 |
BMP includes pollutant sources, regarding waste disposal practices |
"f. Stormwater management. (3)A....Pollutant sources that must be addressed by BMPs, if present, include: viii. Waste disposal practices." |
2284 |
BMP includes pollutant sources, regarding water and drilling fluids storage |
"f. Stormwater management. (3)A.... Pollutant sources that must be addressed by BMPs, if present, include: iv. Produced water and drilling fluids ... |
2269 |
BMP Operators will control stormwater runoff at all oil and gas locations. |
"f. Stormwater management. (2) Oil and gas operators shall implement and maintain Best Management Practices (BMPs) at all oil and gas locations to ... |
2296 |
BMPs include additional facility-specific maps and implementation criteria |
"f.(3)C. Facility-specific maps, installation specification, and implementation criteria shall also be included when general operating procedures and ... |
2300 |
Close drilling pits for reclamation |
"d. Drilling pit closure. As part of interim reclamation, drilling pits shall be closed in the following manner: (1) Drilling pit closure on crop ... |
2254 |
Director conducts onsite inspection if adverse environmental impacts occur |
"b. Additional requirements. Notwithstanding the provisions of the 1000 Series rules, when the Director has reasonable cause to believe that a ... |