BMP ID |
Short Title |
Text of BMP |
---|
9814 |
Align access roads |
"11. Visual Impacts and aesthetics. . . . To the maximum extent practicable, Operator shall comply with the following aesthetic provisions . . . f. ... |
9835 |
Align pipelines with established roads |
"16. Flow lines. . . . To the maximum extent reasonably practicable, any newly constructed or substantially modified flow lines on site shall meet ... |
9829 |
Avoid dust suppression activities within 300 feet of any waterbody |
"14. Fugitive Dust suppression. . . . The operator will avoid dust suppression activities within three hundred (300) feet of the high water mark of ... |
9773 |
Bury temporary water lines at crossings |
"3. Water Supply and Quality. . . . If necessary, Operator will bury temporary water lines at existing driveway and gravel road crossings, or utilize ... |
9811 |
Consult when clearing trees and vegetation |
"11. Visual Impacts and aesthetics. . . . To the maximum extent practicable, Operator shall comply with the following aesthetic provisions . . . c. ... |
9768 |
Containment berm inspection |
"2. Containment berms. . . . All berms and containment devices shall be inspected by the Operator at regular intervals and maintained in good ... |
9767 |
Containment berms |
"2. Containment berms. The operator shall utilize steel-rim berms around tanks and separators at well sites with sufficient capacity to contain 1.5 ... |
9787 |
Copies of water test results provided |
"9. Water Quality Monitoring Plan. . . . c. Copies of all water test results shall be provided to the City and landowner within thirty (30) days of ... |
9738 |
Emergency or Freshwater Pits |
"1. Pits. Operator's Pit Practices within the City. a. . . . emergency or freshwater pits may be allowed if approved by the Colorado Oil and Gas ... |
9843 |
Equipment removal for multi-well pads |
"18. Removal of equipment. . . . It is understood that drilling and completion equipment necessary for multi-well pads may remain on location, so ... |
9841 |
Equipment removed from the site |
"18. Removal of equipment. All equipment used for drilling, completion, or re-completion and maintenance of the facility shall be removed from the ... |
9823 |
Exhaust vented away from occupied buildings |
"13. Air Quality Mitigations. . . . b. To the extent practicable, exhaust from all engines, motors, coolers, and other mechanized equipment shall be ... |
9820 |
First attempt to repair a gas leak |
"13. Air Quality Mitigations. a. In addition to the requirements under Colorado Air Quality Control Program, Title 25, Section 7, C.R.S., oil and gas ... |
9806 |
Floodplain disturbance |
"10. Floodplain. Any disturbance within a 100-year floodplain will be allowed if the Operator has obtained a Floodplain Development Permit from the ... |
9832 |
Flow lines |
"16. Flow lines. Any newly constructed or substantially modified flow lines on site shall be constructed and operated under the provisions of the ... |
9783 |
Hydraulic fracturing chemicals may remain on location during drilling |
"8. Chemical storage. . . . It is understood that hydraulic fracturing chemicals and flowback from hydraulic fracturing on multi-well pads may remain ... |
9821 |
If a gas leak repair is not possible within 24 hours |
"13. Air Quality Mitigations. a. In addition to the requirements under Colorado Air Quality Control Program, Title 25, Section 7, C.R.S., oil and gas ... |
9822 |
If shutting down a well will not stop a gas leak |
"13. Air Quality Mitigations. a. In addition to the requirements under Colorado Air Quality Control Program, Title 25, Section 7, C.R.S., oil and ... |
9831 |
Keep ground free of flammable material |
"15. Flammable material. All ground within twenty five (25) feet of any tank, or other structure containing flammable or combustible materials shall ... |
9815 |
Landscaping practices |
"11. Visual Impacts and Aesthetics. . . . In Urban Mitigation Areas and Useable Open Spaces, one or more of the following landscaping practices may ... |