3893 |
A block survery is highly recommended in order to ensure all the Project is covered by a cultural resource inventory |
D. Cultural Resources Plan: "A block survey is highly recommended in order to ensure that all components of a federal CBNG Project area are covered ... |
3844 |
A Drilling Plan may be submitted for one or more wells |
III. Requirements for the Drilling Plan: "A Drilling Plan may be submitted for a single well or as a Master Drilling Plan for several wells within a ... |
3855 |
A Surface Use Plan submitted for one or more wells where construction and reclamation would be the same in Project |
IV. Requirements for the Surface Use Plan: "A Surface Use Plan may be submitted for a single well or as a Master Surface Use Plan for several wells ... |
3894 |
A Wildlife Monitoring Plan (WMP) gives BLM wildlife information, identifies problems, and makes recommendations through form of application |
E. Wildlife Monitoring Plan: "For Project PODs, a Wildlife Monitoring Plan (WMP) will be provided to BLM to acquire existing wildlife information, ... |
6326 |
Access roads should be designed and constructed to accomodate anticipated traffic and weather conditions. |
Access Roads: "Access roads should be designed and constructed to accomodate anticipated traffic and weather conditions." |
6330 |
Access roads should be located on grades less than 8% |
Access Roads: "Access roads should be located on grades less than 8%, where possible." |
6329 |
Access roads should be located on ridge tops and on gentle upland slopes |
Access Roads: "Access roads should be located on ridge tops and on gentle upland slopes where possible." |
6327 |
Access roads should be located out of or away from snow drifting areas. |
Access Roads: "Access roads should be located out of or away from snow drifting areas." |
6325 |
Access roads should be located to provide safe, year-round travel. |
Access Roads: "Access roads should be located to provide safe, year round travel." |
707 |
Active bald eagle nests within one mile of project related disturbance areas will be monitored between March 1 and mid-July. |
Annual Inventory and Monitoring: Raptors: "Active nests located within one mile of project-related disturbance areas will be monitored between March ... |
8519 |
Actively enforce existing clean air laws |
Rural Life: Doing it Right: "Enforcement: Active enforcement of existing laws is critical to protecting Montana's clean air." |
771 |
Advise personnel to minimize stopping and exiting vehicles in big game winter range in winter. |
Programmatic Guidance for the Development of Project Plans: "Personnel will be advised to minimize stopping and exiting their vehicles in big game ... |
3997 |
Advise personnel to minimize stopping vehicles in big game winter ranger. |
"Personnel will be advised to minimize stopping and exiting their vehicles in big game winter range." |
8515 |
Agencies must conduct thorough biological inventories of each proposed CBM field before production begins |
Wildlife: Doing it Right: "Fish, Wildlife, and Plant Inventories: In order to ensure the long-term viability of Montana's invaluable wildlife, state ... |
8532 |
Agencies must establish clear and enforceable reclamation standards |
Legacy: Doing it Right: "Full Reclamation: To ensure complete reclamation of land disturbed by methane production, state and federal agencies must ... |
8530 |
Agencies must fully comply with NHPA by consulting with all affected tribes |
Heritage: Doing it Right: "Enforcement: State and federal agencies must fully comply with the National Historic Preservation Act by consulting with ... |
8531 |
Agencies must require bonds that cover the full cost of development |
Legacy: Doing it Right: "Bonding: In order to protect Montana taxpayers and encourage responsible development, state andfederal agencies must require ... |
8528 |
Agencies should hold operators fully responsible for violations of laws |
Accountability: Doing it Right: "Fines: State and federal agencies should hold methane operators fully responsible for violations of state and ... |
6339 |
All blooie lines must end a minimum of 30' from the wellbore and be securely anchored. The blooie lines must be in a straight line. |
Drilling and Production Related Field Considerations: "All blooie lines must end a minimum of 30' from the wellbore and be securely anchored. The ... |
6340 |
All casing strings will have centralizers on the bottom three joints of the casing. |
Drilling and Production Related Field Considerations: "The minimum requirement for casing centralizers is all casing strings will have centralizers ... |